September 2016: Wiring conduits were installed by using hydraulic circulation drilling techniques: Workers fix a drill head (Photo: Markus Bernards for FAIR)

  

Latest happenings

Piles: All 1,350 bore piles required to stabilise the subsoil have been built. (more)

Access Roads: Four kilometres of access roads have been built across the site for the construction site traffic.

Pedestrians: During the construction phase, pedestrians and cyclists have to bypass the construction site FAIR prepared a map. (more)

  


To top

Latest aerial photo of the site



Enlarge pic
Aerial photo of the construction site taken on April 22, 2015 (photo: Till Middelhauve for FAIR)

Information for pedestrians and cyclists

Alternative routes for pedestrians and cyclists

 